Oregon CCB Contractor License Exam Exam Prep
Free practice questions

Free OR-CCB Practice Questions

10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

These 10 free OR-CCB questions are organized by exam domain, so you can see how each part of the Oregon CCB Contractor License Exam blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Oregon Const. Contractor Laws and Regulations (18 scored items)

Question 1

A contractor is pricing work on an 18,000-square-foot, 28-foot-high nonresidential warehouse. The contract price of all construction contractor work on the structure for this project is $238,000. For Oregon CCB endorsement purposes, the structure is:

Show answer & explanation

Correct answer: C - Small commercial because all construction contractor work for the project is $250,000 or less

Question 2

A handyman agrees to replace interior trim for $850. The work is casual and minor, and the handyman otherwise meets the conditions for Oregon's under-$1,000 exemption. However, the handyman advertises online to the public as a construction contractor. May the exemption be used?

Show answer & explanation

Correct answer: D - No, because advertising to the public as a contractor defeats this exemption

Question 3

A residential repair agreement begins at $1,850. During performance, the owner authorizes added work, so the contractor now knows the total price will be $2,350. Which action satisfies Oregon's threshold-crossing rule?

Show answer & explanation

Correct answer: A - Deliver the required written contract and notices no later than five days after learning the total will exceed $2,000

Domain 2: Choosing Your Business Structure (4 scored items)

Question 4

Cascade Build LLC has two owners and makes a valid S corporation election for federal tax purposes. Which statement remains accurate after the election?

Show answer & explanation

Correct answer: C - The LLC remains the legal entity; the election changes its federal tax treatment

Domain 3: Hiring and Managing Employees (7 scored items)

Question 5

A drywall installer is free from direction over work methods, holds the required licenses, and is responsible for obtaining other certificates. The installer also has a separate business location and substantial equipment, but bears no risk of loss, serves one customer without marketing, and cannot hire or fire helpers. Under ORS 670.600, what is the best conclusion?

Show answer & explanation

Correct answer: B - The independently established business test is not met because only two of its five criteria are shown

Question 6

A nonexempt carpenter earns $24 per hour and works 46 hours in one workweek. Straight-time wages have already been paid for all 46 hours. What additional amount is due to satisfy the overtime premium?

Show answer & explanation

Correct answer: A - $72

Domain 4: Working with Subcontractors (2 scored items)

Question 7

A subcontractor submits a progress billing. The prime contractor is delivering a check today, but the funds have not cleared. Which document best matches this payment stage?

Show answer & explanation

Correct answer: C - A conditional progress waiver

Domain 5: Contracts (9 scored items)

Question 8

During a remodel, the owner verbally requests upgraded windows that add $7,500 and extend delivery by two weeks. No emergency exists. The superintendent wants to proceed immediately to preserve goodwill. The most defensible contract-administration step is to:

Show answer & explanation

Correct answer: B - Obtain a signed change order covering scope, price, and time before the changed work begins

Question 9

A tile subcontractor installs the specified finishes throughout a house but uses the wrong grout color in one powder room. Correction is straightforward, will not delay occupancy, and does not affect safety or use of the home. How should the breach ordinarily be classified?

Show answer & explanation

Correct answer: D - Minor or partial breach subject to correction or damages

Domain 6: Oregon Lien Law (5 scored items)

Question 10

An Oregon subcontractor last performs substantive contract work on August 20. The improvement is completed on September 5. On September 25, the subcontractor returns only to tighten one screw, solely to try to extend the lien deadline. From which date is the 75-day recording deadline measured?

Show answer & explanation

Correct answer: B - August 20, the earlier of the last substantive furnishing and project completion

The rest of the OR-CCB blueprint

The OR-CCB exam also covers these domains. Drill them in the full free practice test:

That's 10 of 1,030

The full bank has 1,020 more OR-CCB questions with explanations.

Continue in the free practice test →

View plans